Zillmere Multi-Residential Upgrade

Tom Ryan Builders Pty Ltd · QBCC Licence 1311681

Audit Readiness
74%
Current Stage
002 Set Out and Foundations
Nominee
Ryan John McMahon

Stage Workflow

001Preliminary and GeneralApproved
002Set Out and FoundationsIn Progress
003Structural SteelLocked
004Sub Floor FramingLocked
005Wall & Roof FramingBlocked
006Exterior Envelope Construction – FlashingLocked
007Joinery Windows and Doors Openings InstallationLocked
008CladdingLocked
009Metal RoofingLocked
010ElectricalLocked
011PlumbingLocked
012MechanicalLocked
013Passive Fire InstallationLocked
014Internal LiningsLocked
015Wet AreasLocked
016Kitchen, Vanitys, RobesLocked
017PaintingLocked
018External WorksLocked
019Final CompletionLocked

Evidence — Stage 002

  • Form 12 – Surveyor Set OutVerified
  • Form 12 – Soil Geotech / Soil Bearing CapacityVerified
  • Form 12 – Engineering Inspection (Footing, Retaining Walls & Slab)Missing
  • Form 43 – Termite Protection InstallationPending Review
  • Form Work Engineer – Pre-Pour InspectionMissing